Experience means a lot in this business. Years of working on a vast array of projects means you can place your trust in our knowledge and experience.
ORIVNE presents the following case studies demonstrating some of the various environmental projects successfully completed. They are specific projects bid, designed, managed and completed by the principal of Orivne over the past 30+ years. They include large scale projects at facilities such as:
The most important factor in the successful completion of any project is the communication between ownership, consultant/engineer and the right environmental contractor. Orivne understands what it takes to complete the most complex projects on time and on budget, without compromising safety. Orivne is the right environmental contractor for your project.
Each case study gives a brief overview of the specific tasks completed. Orivne looks forward to meeting the challenge of successfully completing your next project.
A detailed plan was formulated and subsequently approved by the U.S. Coast Guard for the safe transfer and shipment of 2.383 million gallons of fuel oil. To move the oil that had been sitting for a number of years, a heating and circulation system was installed on each tank. Once the fuel was fluid, it was transferred via pumps and hose to an awaiting barge on the Sanitary and Shipping canal. Four barges were used and 2.383 million gallons were transferred. Remaining tank bottom sludge, 260,000 gallons, was solidified and properly disposed. The ASTs were cleaned and demolished utilizing an excavator with shear attachment. The terminal building and ancillary buildings were demolished and removed. Zero work place injuries.
The recommendation of screening the material rather than just dig and haul to a landfill saved the client over one million dollars by reusing the existing soils as backfill, preserving precious landfill space and reducing disposal fees. Because less material was hauled off, the project required less backfill to meet local zoning requirements. Zero work place injuries.
Screening the material accomplished the goal of removing the ACM. The remaining materials were segregated by size, relocated, placed and filled in a low lying portion of the property. At the end of the project, the client had over 5+ usable acres of land that was not available prior to starting the project. Zero work place injuries.
A major metropolitan international airport needed the right environmental contractor to perform critical upgrades to their fueling facilities. A number of outlying buildings and facilities also needed to have out of use and orphan USTs removed. The work to be completed was located inside highly secure and sensitive areas of the airport. The team completed all tasks on time and on budget and had zero work place injuries.
The building was completely cleared of hazardous, universal, PCB and bio-hazardous waste prior to demolition. This was accomplished over eight weeks with a ten man crew. Extremely dangerous conditions, including no lighting, open pits and numerous slip, trip and fall hazards were mitigated. All accomplished on time and on budget with zero work place injuries.
A total of eight buildings were part of the scope of work. Each building had a heating oil tank ranging from 5,000 to 25,000 gallons. The tanks were encased in brick and sand used as a fire barrier. Major concerns involved airborne dust and vapors. The project was completed with no major complaints from the affluent tenants and was done on time and on budget with zero work place injuries.
The project was completed on schedule, even with the original scope of work doubling due to unforeseen underground conditions. The Community College building stands today and is a cornerstone of a historic downtown community. Zero work place injuries.
After starting the project, the UST was determined to be located up against an addition that was added on to the existing school. The UST was improperly filled with sand and debris many years ago prior to current UST regulations. Because the UST could not be safely removed without possibly jeopardizing the integrity of the structure, the building foundation was underpinned and supported. The soils inside the UST were removed, hauled and disposed. The UST was safely removed from the ground. Surrounding contaminated soils excavated, hauled and disposed. The excavation was backfilled and resurfaced. All completed during spring break. Zero work place injuries.
The challenge was to remediate an area that was contaminated with tetrachloroethylene inside a 15,000sf active formal wear dry cleaning facility. A vapor barrier was installed from the floor to ceiling isolating the work area from the 32 employees working in the same building. A negative area ventilation system was installed. The contaminated soils were removed, sewer line replaced and the area was backfilled and resurfaced to match existing. All being completed while the facility was fully operational. Zero work place injuries.
The tank farm was properly decommissioned by removing the hazardous liquids, cleaning of the tanks, cutting and disposal of the tank systems including all piping runs, removal of the earthen berms and site grading. All completed on time, on budget and with Zero work place injuries.
Crews worked around the clock with the pipeline company, various local, state and federal agencies to contain, solidify and remove petroleum waste from a ruptured pipeline in a highly populated industrial area. All completed in a high stress environment with zero work place injuries.
Through segregation and onsite sampling, half of the expected contaminated soils were not removed and were placed in an onsite containment system saving the responsible party over half a million dollars in disposal costs. Zero work place injuries.
The galvanizing facility building was completely destroyed due to fire. The acid dip tanks were full of acid and fire debris. The liquids that could be pumped were removed and properly disposed. All debris was removed, hauled and disposed. The acid tanks were then cleaned. The tanks polyethylene tank lining was removed, cut into manageable sections and disposed. The concrete basins were demolished and disposed. The area was graded and backfilled. Zero work place injuries.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.